There is no official rate for excavator hours. Your hourly rate has two parts. The machine: depreciation, interest, insurance, servicing, wear parts and diesel, divided by the hours it actually works in a year. The operator: wage, social security contributions and unproductive time. The lower the utilisation, the higher the rate you need. Delivery and collection, and attachments such as a breaker or sorting grab, go on the invoice as separate lines.
With measured quantities (Ausmass), you agree a unit price per m³, m² or linear metre and bill the quantity actually done. State in the quote whether volume is measured in place (undisturbed ground) or loose (on the tipper), and have the site manager countersign the measurements. If no fixed price is agreed, you are paid according to the value of the work and your expenses (Art. 374 Swiss Code of Obligations, CO). A fixed price, on the other hand, binds you even if the ground is harder than expected (Art. 373 CO).
Construction waste must be separated on site, and clean excavated material kept as unmixed as possible (Art. 17 of the Waste Ordinance, VVEA/OLED). It must be recovered as fully as possible, for example as building material or for backfilling (Art. 19 VVEA). Tipping fees and haulage that you pass on are part of the price and therefore of the VAT base, even if you show them separately (Art. 24 para. 1 VAT Act). Bill them per tonne as per the weighbridge ticket.
Without an agreement, payment is only due on handover (Art. 372 CO). So interim payments as work progresses and a retention until acceptance only apply if they are in the contract. The SIA 118 standard is a private set of rules and only applies if you expressly make it part of the contract. If an invoice stays unpaid, you can have a builder's lien (Bauhandwerkerpfandrecht) registered, no later than four months after the work is completed (Art. 839 para. 2 Swiss Civil Code). More on the deposit invoice.
The law provides no reduced rate for machine hire (Art. 25 para. 2 VAT Act), so the standard rate of 8.1% applies. You must register for VAT (MWST/TVA) from CHF 100'000 annual turnover (Art. 10 para. 2 let. a VAT Act). The official net tax rates (Federal Tax Administration ordinance, as at 1.1.2025):
| Activity | Net tax rate |
|---|
| Excavation firms | 4.5% |
| Earthmoving (loader) firms | 4.5% |
| Demolition firms | 4.5% |
| Building and civil engineering firms | 4.5% |
| Machinery: hire with or without operator | 3.7% |
| Construction machinery and equipment: trade | 1.3% |
| Labour-only work in construction | 6.8% |
Since 2025, every activity with more than 10% of turnover gets its own rate (Art. 86 VAT Ordinance). If you buy expensive machines, you have a lot of input tax, so compare the effective method with your accountant. More in VAT for freelancers.
According to SECO, the national collective agreement for the main construction trade (Landesmantelvertrag, LMV; CN in French) is generally binding until 31.12.2031, except in parts of the cantons of Geneva and Vaud. It covers employers whose main activity is civil engineering, road building, excavation, demolition, or the storage and recycling of excavated and demolition material. There is no federal excavator licence. According to Suva, however, anyone operating construction machinery with a driver's seat needs training under Art. 8 of the Accident Prevention Ordinance (VUV/OPA), whatever the weight of the machine, and the employer documents it. The cantons of VS, VD, GE and NE have additional rules.
Magic Heidi fits excavation contractors, small civil engineering and demolition firms, skip hire services and construction equipment rental businesses that want to handle quotes, daywork and quantity invoices, interim invoices, hire invoices, receipts and VAT without office staff. Not included: NPK bills of quantities and costing, quantity take-off software, a site diary signed on a tablet, rental fleet management with availability calendar and bookings, weighbridge integration, purchase credit notes at daily prices for the scrap metal trade and payroll under the LMV. You keep daily reports on paper or in your report app and store them in Magic Heidi with the client. If you price public tenders to NPK, run large sites with full construction administration or dispatch a rental fleet of dozens of machines, construction or rental software is the better choice.